Is the owner of the building or contractor demolishing the building be responsible for submitting a notification?

The NESHAP regulation states that either the owner of the building or the operator of the demolition or renovation operation can submit the notification. Usually, the two parties decide together who will notify. If neither provides adequate notice, either or both parties can be held liable.

Show All Answers

1. What is a notification?
2. Is the owner of the building or contractor demolishing the building be responsible for submitting a notification?
3. To meet the 10-day waiting period do I give the start date of demolition or of the asbestos removal?
4. Does the 10-day notification requirement refer to calendar or working days?
5. When should a notification be revised?
6. I am demolishing or renovating a relatively new building. Do I still need an asbestos inspection?
7. Is moving a building regulated by the Asbestos NESHAP?