To meet the 10-day waiting period do I give the start date of demolition or of the asbestos removal?

For demolition, the start date is the date that the removal or related activity begins. The demolition start date must be reported. The waiting period should be calculated based on the start date of the removal or the demolition if no removal is required. The waiting period is necessary to give inspectors time to visit the site before activity begins